top of page

How Much Does a Padel Court Cost in the U.S.?

Padel One Courts construction and design team placing glass panels on site.
Padel One Courts construction and design team placing glass panels on site.

Most U.S. padel courts fall within a defined cost range depending on site prep, structure (steel + glass), surfacing, lighting, freight, permits, and installation. Florida projects may add corrosion-resistant finishes and hurricane-ready engineering that increase price but improve durability and safety over the long term.





What Drives the Cost (The Short Answer)

  • Site & Base: Concrete slab, drainage, utilities

  • Structure: Steel frame, glass, mesh, anchoring hardware

  • Play Surface & Lighting: Turf, sand infill, LED poles and controls

  • Freight, Permits, Installation: Shipping, staging, crew, and approvals

  • Upgrades: Roof/canopy, premium coatings, acoustic or privacy options, branding

  • Location Factors: Site access, coastal exposure, local codes, inspections


Typical Line-Item Breakdown (Reference)

Use this as a guide to understand where most of the investment goes.Actual numbers depend on site conditions, configuration (single vs. multi-court), and chosen finishes.


Category

What’s Included

Notes for Buyers

Site Prep & Base

Survey, excavation, drainage, rebar, concrete slab

The concrete foundation typically represents about 40% of the total project cost. A 6-inch reinforced (rebar) concrete base is recommended to securely anchor the court and resist strong winds—especially in hurricane-prone areas. Proper drainage extends the court’s lifespan.

Padel Court

Steel columns, beams, tempered glass, welded mesh, synthetic turf, sand infill

The structure, glass panels, and turf together represent roughly 30% of total cost, driven by material quality, resistance level, and model type. Premium coatings and stainless hardware improve corrosion resistance in coastal zones.

Installation

Crew labor, machinery, assembly, final testing

Installation accounts for about 15% of total cost, depending on the crew’s experience and efficiency. Well-planned multi-court projects benefit from faster assembly and lower per-court costs.

Freight & Logistics

Transport, customs (if applicable), on-site staging

If the court is stocked in the U.S., shipping typically adds less than 5%. If the structure is imported from abroad, freight can reach 10–15% depending on distance, customs, and logistics.

Permits & Professional Fees

Engineering stamps, design plans, permit fees, inspections

While this represents a smaller percentage of the total, it often requires time for design approvals and coordination with local authorities. Planning this early prevents delays.

Approximate Cost Distribution

  • Concrete Base: ~40%

  • Structure, Glass & Turf: ~30%

  • Installation: ~15%

  • Freight: 10%

  • Permits & Design: 5%

Percentages vary based on project scale, site complexity, and origin of materials.


What Can Increase—or Reduce—Your Budget

Increases:Difficult access, extensive permitting, roof/canopy additions, premium fixtures, or one-off custom designs.


Reductions:Building multiple courts at once (shared mobilization), standard configurations, and early material procurement to avoid stock shortage and extra timing.


Florida-Specific Considerations (Worth It Over the Long Run)

  • Wind Engineering: Structural anchoring and reinforced specs for hurricane zones.

  • Corrosion Control: Hot-dip galvanization + powder coat, stainless hardware, and marine-grade fasteners.

  • Lighting & Electrical: Code-compliant pole bases, surge protection, smart controls for energy savings.

  • Maintenance Plan: Salt-air cleaning and periodic inspections extend life and preserve warranty coverage.


Timeline & Process (What to Expect)

1️⃣ Discovery & Viability (1–2 weeks) – Define goals, location constraints, and site photos/plans.

2️⃣ Pre-Construction (2-5 months) – Design, permits, layout and approvals.

3️⃣ Site Prep & Base (1–2 weeks) – Excavation, drainage, concrete pour and cure.

4️⃣ Logistics (1–4 weeks) – Shipping, access, machinery, unloading, installation team traveling.

5️⃣ Installation (1 week) – Frame assembly, glass panels, turf installation, sand infill, LED setup.


Multi-court clubs often progress faster per court thanks to shared mobilization and parallel crews.


Frequently Asked Questions (FAQ)

Can we phase one court now and another later? Yes. Plan the slab layout and utilities from the start so additional courts can be added seamlessly.


What about noise and neighbors? Acoustic panels, controlled lighting, and operating-hour policies minimize impact. We’ll align design specs with your site’s specific context.


What to Do Next




bottom of page
Padel Ball Image Get a Free Quote Padel Ball Image